I have a question,

I have a question, sometimes you have a job and it did just not cut trough all the way. Is it possible during operation to give the Z a command to go down another 0,2 mm ? during the cut ?.
Also if I have 2 peaces in a G codes can I say to not cut one peace but only cut the other ?

My trick on the Z is to simply go down 0.2mm and then set that as my new Z zero using the pulldown in the Axes widget for the Z value. Then I run the job again.

On the 2 pieces in a Gcode, the one trick you could use it put an M6 tool change between the two pieces and make sure ChiliPeppr is configured to pause on tool changes (it is by default). Then just don’t run the 2nd part of the job.